Inputs to result
Concrete cu ft = (wall length × wall height − openings in sq ft) × thickness in inches ÷ 12; divide by 27 for cubic yards.
Concrete & Masonry
Estimate poured concrete wall volume in cubic yards and cubic feet while subtracting window and door openings and adding order allowance.
Enter wall length, height and thickness. Subtract the combined opening area before applying the chosen order allowance.
Calculation and worked example reviewed 2026-11-12. See our calculation methodology.
220 sq ft net wall × 8 in thickness.
5% order allowance shown separately.
Formula and example
This estimator converts your entered jobsite inputs (wall length, wall height, openings to subtract, wall thickness, order allowance) into consistent US trade units, computes the exact geometric baseline first, and then applies any selected waste or order allowance so you can verify both numbers before purchasing materials.
where:
Concrete cu ft = (wall length × wall height − openings in sq ft) × thickness in inches ÷ 12; divide by 27 for cubic yards.
A 30 ft × 8 ft wall, 8 in thick, with 20 sq ft of openings has 146.67 cu ft of concrete, or 5.43 cu yd before allowance.
Geometric volume for an 8 ft tall wall before subtracting window/door openings.
| Wall Length | 6 in Thick Wall | 8 in Thick Wall | 10 in Thick Wall |
|---|---|---|---|
| 20 ft length | 2.96 cu yd | 3.95 cu yd | 4.94 cu yd |
| 30 ft length | 4.44 cu yd | 5.93 cu yd | 7.41 cu yd |
| 40 ft length | 5.93 cu yd | 7.90 cu yd | 9.88 cu yd |
| 60 ft length | 8.89 cu yd | 11.85 cu yd | 14.81 cu yd |
The opening deduction is a simple area subtraction. Footings, pilasters, thickened edges, keyways, form loss and structural wall design are separate checks.
Yes. Enter their combined wall-face area. Confirm whether small penetrations warrant a deduction on the actual job.
No. Calculate the footing separately and add its volume to the wall quantity.